TIMELINE for Case: 3246/Cv-C/2021
Humaida A Ghafoor v. Government of Maldives
Civil litigation to stop the Gulhifalhu Port Development Project, Maldives

Start 🔽 02 September 2021

02 March 26

Last minute cancellation after scheduling the final hearing of the main case with a long advance notice period

• As observed in the 20 January 2026 update below, the Civil Court scheduled the final hearing for the main case for today at 10.00am, following a prolonged delay in reaching its final decision. However, less than an hour before the hearing, we received an email at 9.09am informing that today’s hearing has been cancelled.

• Today’s scheduled hearing is the first hearing for which scheduling was done with a long advance notice period. However, it is concerning that today’s hearing has not gone ahead as scheduled and got cancelled, considering that it has been some time since the legal timeframe for delivering a verdict had expired.

• The legal process for this is provided below.
Section 259(a) of the Civil Procedure Code of Maldives (Law No. 32/2021) states that:
“Once the hearings of a civil action come to a conclusion, a decision must be made immediately or as soon as possible.”
Moreover, s.259(b) states that if a decision is not made immediately, a date for the decision must be given to the parties involved and if that is not possible, a decision date must be shared with the parties within 3 days of the last hearing of the case. In our case, the court has not acted within these legal requirements.
According to s.259(c):
“The date set under sub-section (b) of this section must not be a date that is later than 30 (thirty) days after the date of the last hearing.”

20 Jan 26

Final hearing of the main case scheduled, following Civil Court’s prolonged decision delay after the concluding statement

• In our 02 September 2025 update, we noted that the Civil Court had not made a decision in the main case following the 7th hearing, despite the fact that the legal timeframe for this had long expired. 

• However, we received a summons from the Civil Court on 12 January 2026 stating that the final hearing for the main case has been scheduled for 02 March 2026 at 10.00am at the Civil Court.

• This case was filed on 02 September 2021, and accepted by the Civil Court on 19 September 2021.

02 Sep 2025

Concern about Civil Court’s decision delay following the concluding statement of the main case at the 7th hearing

• The hearing held on 20 April 2025 at the Civil Court regarding the main case to stop the reclamation at K. Gulhifalhu was to present the concluding statement of the case. It was expected that where the court required no further clarification in connection with the statements, the next step would be to present the court’s decision. However, the court has neither requested for further clarification, nor decided on a date for the decision hearing.

• Although 4 months have elapsed since that hearing, the Civil Court has still not announced its decision. This is a matter of great concern, as this situation is in contravention to the existing legal procedures.

• Section 259(a) of the Civil Procedure Code of Maldives (Law No. 32/2021) states that:
“Once the hearings of a civil action come to a conclusion, a decision must be made immediately or as soon as possible.”
Moreover, s.259(b) states that if a decision is not made immediately, a date for the decision must be given to the parties involved and if that is not possible, a decision date must be shared with the parties within 3 days of the last hearing of the case. In our case, the court has not acted within these legal requirements.
According to s.259(c):
“The date set under sub-section (b) of this section must not be a date that is later than 30 (thirty) days after the date of the last hearing.” (unofficial translation)
However, the court has not complied with this sub-section either.

• Although the Civil Procedure Code provides clear legal procedures for reaching case decisions, it is deeply disturbing to observe the Civil Court’s non-compliance with the law in this case. In this context, our attempts to obtain updates from the court has not yielded any constructive responses to date.

• Today marks 4 years since the initial submission of the main legal action of this case to the Civil Court on 02 September 2021, which continues to languish in this first instance lower court stage. During this time, we observed that the manner in which the case has been handled by the court suggested that the public interest civil remedy sought in this case cannot be achieved in a law court in the Maldives.

• We note that the age old legal maxim ‘justice delayed is justice denied’ applies perfectly to this civil litigation case. Nevertheless, it would be every citizen’s hope that a court in the Maldives has the ability to conduct a fair trial in the public interest and conclude it within a reasonable timeframe, in compliance with applicable due legal processes.

20 Apr 2025

20 April 2025 - CC hearing [Miveshi Maldives]

Update of the 7th hearing for the main case at the Civil Court

• The summons for the 7th hearing scheduled for today, 20 April 2025 was sent by the Civil Court on 07 April 2025, and today’s scheduled hearing at 11.50am began at 12.03pm and concluded at 12.55pm.

• Today’s hearing was held to discuss the concluding statements of the case. On 03 April 2025, the Civil Court instructed by email for both parties to submit their concluding statements to the Court by 15 April 2025.

• The Claimant submitted the concluding statement with reference to the key issues raised in the case. At today’s hearing, the Claimant highlighted that from its commencement, the Respondent (State) had operated in contravention to laws in the K. Gulhifalhu project, and that during implementation, the State had not complied with any of the conditions specified in the EPA’s Decision Statement that approved the project EIA. Therefore, it is clear from the submitted evidence that the project has been causing irreversible damage to the environment in the project area, and as a direct consequence, impose negative social and economic impacts on the people living in the affected area. Moreover, the Claimant stated that the evidential material submitted in this case provides clear proof that the implementation of this project contravenes Article 22 of the Maldives Constitution and related laws and regulations to protect and preserve the environment.

• In their concluding statement, the Respondent primarily stated that the project was in compliance with the relevant laws and that the legal remedy sought by the Claimant was outside the jurisdiction of the Court.

• Unless the Court requires further clarification on any matter, the next step in this case is likely to be the concluding judgment. However, the Ghazee did not specify a date for the next hearing.

17 Mar 2025

Civil Court 17 March 2025 MIVESHI team

Update of the 6th hearing for the main case at the Civil Court

• The summons for the 6th hearing scheduled for today, 17 March 2025 was sent by the Civil Court on 10 March 2025, and today’s scheduled hearing at 11.50am began at 12.26pm and concluded at 13.09 (approximately 43 minutes).

• Today’s hearing was an evidence hearing where both parties were given the opportunity to discuss the submitted witness testimony. The Claimant had submitted as witnesses 2 of the most prominent and experienced divers in the Maldives, Hussain Rasheed (Sendi) and Mohamed Seeneen (Sindhi).
(Note that their testimony had to be taken twice. Details of this is given in the 19 March 2024 update provided below in this timeline).
The Respondent (State) had submitted the Director General of the Environmental Protection Agency (EPA) Ibrahim Naeem as their expert witness.

• The State advocated that the Claimant’s witnesses were “ordinary witnesses” and that their testimony cannot be recognised as “expert evidence”. However, there is no such thing as “ordinary witnesses” in law, and there is no clarification provided that distinguishes between “expert” and sector professionals of long experience. In response to this point by the State, the Claimant referred to s.13 and s.121 of the Evidence Act (11/2022) which provides there is no legal barrier to recognising such expert testimony. The Claimant further requested the Court to recognise Sendi and Sindhi’s testimony as primary evidence.

• The Claimant clarified to the court that the witnesses who provided their first-hand experience and eye-witness testimony of the negative impacts of reclamation on the reef ecosystem, including marine protected areas, gave information that aligned with the scientific documentary evidence submitted to the Court about the same. Notably, the State had sought to nullify this witness testimony by resorting to a semantic debate instead of relying on legal provisions. At today’s hearing, the Claimant raised a complaint to the Court about the disrespect directed towards her expert witnesses by the State at the testimony hearing, in an attempt to nullify the validity of their testimony.

• The issue was raised by the Claimant at the 19 March 2024 witness testimony hearing also, that the State’s single witness, Director General of the EPA Ibrahim Naeem is not legally allowed to give testimony in this case. This is because in addition to Ibrahim Naeem being the head of the EPA which is one of the three Respondents in this case, he is also the signatory who approved the Decision Statement permitting the K. Gulhifalhu reclamation project and its Environmental Impact Assessment (EIA) of April 2020. This conflicts with s.51 of the Evidence Act (11/2022).
(Details of this is provided below in the 19 March 2024 update in this timeline).
In addition, at today’s hearing s.122(b)(3) and (6) were cited in support of this point of law.

• At today’s hearing, both parties were allowed one opportunity to discuss witness testimony. One reason for this is because the presiding Qazi wanted to shorten the hearing due to it being Ramadan. With reference to the witness testimony discussion today, the Qazi did not make a decision whether to accept or dismiss any of the witness testimony.

• The next hearing would be held to present concluding statements of the case. Presiding Qazi Uz. Farhad Rasheed announced that the next hearing of the case would be held around 20 April 2025. This is because the long public holiday break for the last 10 days of Ramadan is imminent, after which, the Eid holidays will follow. Qazi Uz. Farhad observed that due to the heavy documentary content of the case, both parties would need ample time to prepare. The State Attorney said that currently, he is the person assigned to this case and given that he recently took the case afresh, he would need time to prepare. I do not believe that this should be an issue that should arise at the Attorney General’s Office (AGO). This is because I believe that cases overseen by the State ought to be managed by teams of attorneys in an organised manner. The fact that a case of this scope is being assigned afresh to one person indicates the existence of management gaps that need improving at the AGO.

24 Feb 2025

Court hearing Miveshi Maldives [24 Feb 2025]

Update of the 5th hearing for the main case at the Civil Court, following the 19 March 2024 witness testimony hearing

• In the main case to stop the port development project at K. Gulhifalhu, witness testimony was first taken at the Civil Court at a hearing held on 14 March 2023, at the 4th case hearing. However, due to a technical issue at the Civil Court, the hearing recording file was corrupted, leading to a repeat hearing held on 19 March 2024 (one year later). Following this, the administrative processing of the witness testimonies (transcription etc) were completed in October 2024.

• The summons for the 5th hearing scheduled for today, 24 February 2025 was sent by the Civil Court on 16 February 2025, and today’s scheduled hearing at 11.45am began at 12.02 and concluded at 12.08 (approximately 6 minutes).

• Although today’s hearing was to discuss the witness testimonies, a summary statement of witness testimonies was shared with the court by the Claimant, and the same requested from the State.

• At today’s hearing also, Qazi Uz. Faruhad Rasheed made note of his concern about the delays in progressing the case citing resource limitations and challenges faced by the Court, recognising that the Claimant would want to expedite the case.

• At today’s hearing, it was observed that the State Attorney representing the Attorney General’s office is a completely new attorney on this case.

• As per the Claimant’s request, the Qazi instructed the State to submit a written statement on witness testimonies. The earliest possible date the State could submit this was identified as Thursday, 6 March 2025, hence the Court instructed the State to observe this submission date.

• The Qazi announced that in order to expedite the case, the hearing to discuss witness testimony would be scheduled for Sunday 9 March 2025. Following that, a date would be set to submit the final statements in this case.

20 Dec 2024

Additional update on the Supreme Court’s response regarding the request to review its 15 May 2024 decision on the temporary stop order

• In the 8 October 2024 update of this timeline, it was noted that the response from the Supreme Court signed by the Chief Justice Ahmed Muthasim Adnan on 6 October 2024 is the final decision in this TSO case. It was also noted that as it was unclear which Judges participated in reaching this decision at the meeting of the Supreme Court’s General Council, efforts would be made to clarify this.
 
• Therefore, on 9 October 2024, a right to information (RTI) request was submitted to the Supreme Court under the Right to Information Act (Law No. 1/2014) to clarify which Judges participated in the General Council meeting at which the TSO review request was decided.
 
• On 24 October 2024, the Supreme Court communicated a response to the RTI request, via email. Based on the information provided, the following 6 Judges participated in the General Council meeting of the Supreme Court where the review request decision was made.
1) Chief Justice Ahmed Muthasim Adnan
2) Judge Dr Azmiralda Zahir [*]
3) Judge Mahaz Ali Zahir
4) Judge Husnu Al Suood [*]
5) Judge Ali Rasheed Hussain [*]
6) Judge Dr Mohamed Ibrahim.

• The above list of 6 Judges includes the 3 Judges [*] that presided over the TSO case. However, the Supreme Court noted in its communication that: “The rules of practice of the General Council is for Judges involved in deciding a case submitted to the General Council to recuse themselves from any decision-making discussion relating to that case.” Therefore, the Supreme Court’s information suggests that the  decision to reject the review request, be it through discussion or a vote, was made by the Chief Justice Ahmed Muthasim Adnan, Judge Mahaz Ali Zahir and Judge Dr Mohamed Ibrahim.

• The reason for submitting a request to review the TSO decision is because of our firm belief that the Supreme Court’s decision had categorically set aside and contravened laws and involved fundamental errors. (Further details of this are provided in the 11 August 2024 update below as well as this analysis.) Considering the above manner in which matters involving the TSO decision in this case has unfolded, it is evident that 6 Judges of the Supreme Court rejects our claims that the Court’s decision had set aside and contravened laws and committed a gross injustice, and also rejects the points of law and procedure submitted in support of a review of the TSO decision of the Supreme Court.

• In this case involving litigation against the State by a citizen, the Maldives High Court decided in my favour having conducted exceptionally thorough legal research, evidential consideration and application of the law to the facts (further details relevant to this are available in the 14 February 2024 update in the timeline below). However, it is possible to assert that the manner in which the Supreme Court handled the State’s appeal process of the High Court’s judgment at the Supreme Court is indicative of the prevailing political instability in the country. I am inclined to believe that in the end, this case had become the victim of a political as opposed to a legal judgment. As a citizen, it is deeply troubling that in this case, the Maldives Supreme Court has proved reluctant to uphold both national and international law recognised by the Maldives. In my view, a necessary change required for the public interest is for the Maldives Supreme Court to become an independent institution of the judicial sector with the capacity to prioritise upholding rule of law and justice.

08 Oct 2024

Supreme Court’s response regarding the request to review its 15 May 2024 decision on the temporary stop order

• Due to serious concerns about the Supreme Court’s decision number 2024/SC-A/08 of 15 May 2024 regarding the temporary stop order to halt the reclamation project at K. Gulhifalhu, a request to review the decision was submitted to the court on 11 August 2024. The court acknowledged receipt of this submission on 15 August 2024.
 
• On 11 September 2024 (1 month to the day the submission was made), a letter was sent to the Supreme Court to clarify the status of the submission due to the long delay and silence in the registration process. However, no response was received in connection with this letter.
 
• On 6 October 2024, a response was received in connection with the 11 August 2024 review submission form. The response of the court raises serious concerns.
 
• The review submission was made with reference to section 3 of the ‘Submission Form to Review a Decision of the Supreme Court’, specifically subsections (1) and (3).
Section 3 reads as below.
3(1) – the decision categorically set aside and contravened laws
3(2) – new evidence comes to light after the decision where such evidence shows the occurrence of a gross injustice
3(3) – or the occurrence of a gross injustice for any other reason
(unofficial translation of section 3)
With reference to subsection (1), the review request was submitted due to the belief that the court’s decision had categorically set aside and contravened laws, detailing points of law to support that claim. With reference to subsection (3), the review request was submitted detailing that the Supreme Court’s decision clearly involved gross injustice.
 
• In the response letter received from the Supreme Court on 6 October 2024, signed by the Chief Justice Ahmed Muthasim Adnan, it was stated that the review submission was found to have no cause for such review by the Supreme Court’s General Council number SFMJ/2024/22 held on 24 September 2024.
It is evident from the response that the General Council of the Maldives Supreme Court rejects the claims that the decision in question has contravened laws and commits gross injustice.
 
• It is not clear which Justices were at this meeting of the General Council. Therefore, efforts will made to clarify this important point. The Maldives Supreme Court has a total of 7 Justices. According to section 137(c) of the Regulations of the Supreme Court (2020), the quorum of a General Council meeting must not be less than 3.
 
• The decision of the Supreme Court to reject the requested review is deeply concerning. This is because we believe that decision number 2024/SC-A/08 is fraught with legal errors in application involving gross injustice. Following the Supreme Court’s General Council decision of 24 September 2024, any opportunity to obtain a judicial remedy from a national court in the Maldives regarding the interim injunction against the K. Gulhifalhu reclamation project is now closed. This is also clear from section 24(c) of the Regulation of the Supreme Court (2020). However, we believe that this decision has the effect of undermining trust and confidence that the Supreme Court would uphold the law and its principles and deliver just decisions.

11 Aug 2024

Supreme Court [11 Aug 2024] #saveMaldives

Request to review the Supreme Court’s decision of 15 May 2024 on the temporary stop order

• The High Court’s decision in judgment number 2023/HC-A/267 of 14 February 2024 regarding the application for a stop order (interim injunction) to halt the K. Atoll Gulhifalhu reclamation project was appealed by the State at the Supreme Court on 15 February 2024.
 
• In its decision of 15 May 2024, the Supreme Court ruled to nullify the High Court’s decision to grant a stop order. A series of concerns about this decision was published previously on Miveshi on 16 May 2024. (See brief analysis of the judgment)
 
• In addition to this, due to the contention that the Supreme Court’s decision had certain fundamental errors and disregard to laws and legal principles, using the Supreme Court’s procedure through the “Application form requesting to review a decision of the Supreme Court”,  a request was submitted today, 11 August 2024, to review the court’s judgment number 2024/SC-A/08.
 
• Although a decision of the Supreme Court is final, due to the fact that fundamental errors had been made historically in the court’s decisions in certain instances, a review procedure of such decisions had been introduced in the Maldives context. The reason for using that procedure to submit a request for review is due to having serious concerns about the court’s decision in this matter.
 
• Although the review request is at the registration stage at this point in time, it is hoped that in light of the submitted concerns, the Supreme Court will accept this review submission.

15 May 2024

State’s Appeal of the High Court’s Decision at the Supreme Court – Update – Fifth Hearing – Decision

• Following the State’s fourth appeal hearing at the Supreme Court on 06 May 2024, the fifth hearing was scheduled for 6 May 2024 at 09.45am. The public hearing was conducted via Microsoft Teams from 10.01am to 10.29am today.
 
• Today’s hearing was conducted by the Supreme Court’s following 3 judge bench:
1) Judge Uz. Ali Rasheed Hussain (Chair)
2) Judge Dr. Azmiralda Zahir
3) Judge Uz. Husnu Suood
 
• The unanimous decision of the 3 judge Supreme Court bench was that the decision of the High Court in this appeal case was unlawful and therefore declared void by the Supreme Court.
 
• Judge Dr Azmiralda Zahir concurred with the opinion of Judge Uz. Ali Rasheed Hussain. Judge Uz. Husnu Suood also did so, after making note of some additional points.
 
• An analysis of some of the key points in the Supreme Court’s decision is separately available at this link.
 
• Overall, the message received from this Supreme Court decision is that the existing environmental protection laws in the Maldives do not have to be implemented or upheld by the implementing authorities to serve the purpose for which they are made. Additionally, the destructive projects carried out by foreign companies can be conducted outside the national legislative structure in ways that favour them, with the State as a protective shield to continue such projects. In this situation, the basic rights of citizens and the public interest can be set aside.
Supreme Court’s Decision PDF (Dhivehi) [15 May 2024]

Supreme Court’s Decision PDF (Unoffical English translation)
[added: 17 June 2024]

06 May 2024

State’s Appeal of the High Court’s Decision at the Supreme Court – Update – Fourth Hearing

• Following the State’s third appeal hearing at the Supreme Court on 28 April 2024, the fourth hearing was scheduled for 5 May 2024. However, this was rescheduled to today, 6 May 2024 at 09.45am. The public hearing was conducted via Microsoft Teams from 10.05am to 10.51am today.
 
• Today’s hearing was conducted by the Supreme Court’s following 3 judge bench:
1) Judge Uz. Ali Rasheed Hussain (Chair)
2) Judge Dr. Azmiralda Zahir
3) Judge Uz. Husnu Suood
 
• The State continued to complete its rebuttal statement at today’s hearing, as this was not completed at the third hearing. The Chair of the Judges’ bench observed that more time than usual had been given to hear the substantive arguments in this case and at today’s hearing, each party was given 10 minutes to provide any further comments. Time was given to both parties to answer questions from the Justices and to give brief concluding comments.
 
• Following are some notable points from the questions from the Judges.
1) Noting that the Appellant State had said project stoppage would cause significant financial damages, Judge Uz. Ali Rasheed Hussain asked whether documentation had been submitted on this point and to clarify the amounts involved. In response, the State said that documentation had been submitted and the damages constitute “idle charges” at Euro 6,000/- (six thousand) per hour and “standby periods” at Euro 17,700/- (seventeen thousand seven hundred) per day.
(( On this point, it is notable that at the first Supreme Court hearing of this case on 13 March 2024, the amount cited is different, which was that “idle charges” would cost the State Euro 15,300/- (fifteen thousand three hundred)  per hour.))

2) In connection with the above question, Judge Uz. Husnu Suood asked whether the agreement included any exception clauses such as due to reasons of natural (disasters) or environmental damage. In response, the State said that there were no such exception clauses in the agreement.
 
3) The additional question posed by Judge Uz. Husnu Suood was whether the agreement was vetted by the Attorney General’s Office (AGO). The State responded saying that as a general rule, the procedure is that such agreements would be seen by the AGO. However, in this case, this did not happen and the AGO had sight of the documents in connection with this case. This information suggests that the Gulhifalhu reclamation project agreement did not follow the established administrative protocols.
 
4) Noting the claim by the Respondent that approximately 50 islands had been subject to land reclamation, Judge Uz. Ali Rasheed Hussain asked whether the damage caused by this had been rectified or reversed. In response, the Respondent said the available evidence suggests that such information is not available, citing the example of the dearth of post-project impact monitoring for the 2016 Feydhoo reclamation project, observed in the 2022 EIA for the Addu Atoll land reclamation project. It is not common practice to do follow up research to establish the impact of damage caused by such projects, so there is an issue of absence of such research, preventing a direct answer to the Judge’s question. A 2015 scientific paper on the impact of the 1998 mass coral bleaching event in the Maldives showed that recovery was not complete.
 
• Closing today’s hearing, the Chair of the Judges’ bench said that the case will be concluded at the next hearing, although a date was not set for the next hearing today.
Video

28 Apr 2024

State’s Appeal of the High Court’s Decision at the Supreme Court – Update – Third Hearing

• One month after the State’s second appeal hearing at the Supreme Court on 28 March 2024, the third hearing was scheduled for today, 28 April 2024 at 10.45am. The public hearing was conducted via Microsoft Teams from 11.03am to 12.00pm today.
 
• Today’s hearing was conducted by the Supreme Court’s following 3 judge bench:
1) Judge Uz. Ali Rasheed Hussain (Chair)
2) Judge Dr. Azmiralda Zahir
3) Judge Uz. Husnu Suood
 
• Due to time limitations, the Respondent’s response to the State’s points of appeal were not completed at the second hearing. Therefore, time was allowed to complete this at this hearing. The State was given the opportunity to respond in return, although the hearing was adjourned at 12.00pm before this response was complete.
 
• Some of the responses given to rebut the State’s points of appeal at this hearing are as follows.
1) At the 28 March hearing, Judge Husnu Suood asked multiple questions in relation to the long term impacts of sedimentation on corals and whether reefs can revive following such impacts. At today’s hearing, a more comprehensive response was provided to clarify these questions, using scientific research on such impacts including site-specific experiential information available from the Maldives.
2) The opportunity was given to elaborate on the State’s 4th point of appeal to which a response was given at the 28 March hearing. The cost of project monitoring was presented at that hearing, which is estimated between USD 1.7 to 1.8 million with the assertion that despite the high cost, such monitoring is weak and inadequate. It was clarified to the court at today’s hearing that this monitoring is done by a party appointed by the contractor, who are also the party that conduct the EIA in favour of the project. The significance of the issue of conflict of interest in these processes was highlighted.
3) Response was given to the State’s 5th point of appeal, one part of which claimed that the High Court’s decision had the same effect as the remedy sought by the substantive case. It was explained to the court that there is no basis for this claim, citing relevant case law. Additionally, it was presented to the court that the State’s claim about the inaccuracy of the application of the Nexbiz criteria in this case also has no basis, citing case law and legal principles used in such cases in other jurisdictions.
4) A point of note in today’s response was that an announcement was made by one of the State’s Appellants, the Ministry of Construction and Infrastructure on 16 April 2024, stating that the land reclamation for the second phase of the Gulhifalhu project had been completed. As such, it was highlighted to the court that in this case, the Maldivian State, including the Courts and other relevant authorities have all failed to uphold the country’s laws established to protect the environment.
 
• Closing today’s hearing at 12.00pm, the Chair of the judges bench said that as the State had not finished giving their responses, opportunity will be given at the next hearing to do so and for the Respondent to respond, as well as time to answer questions from the Judges.
 
• After today’s hearing, the Supreme Court has issued a summons stating that the 4th hearing of this case has been scheduled for 8.45am on Sunday 5 May 2024.
Video
Humaida Abdul Qafoor Vs Ministry Environment 3

28 Mar 2024

State’s Appeal of the High Court’s Decision at the Supreme Court – Update – Second Hearing

• Following the State’s first appeal hearing at the Supreme Court on 13 March 2024, the second hearing was schedule for today, 28 March 2024 at 10.15am. The public hearing was conducted via Microsoft Teams from 10.35am to 11.30am today. Due to a technical issue, the hearing was interrupted for a moment, but resumed and completed without any further interruptions.

• Today’s hearing was conducted by the Supreme Court’s following 3 judge bench:
1) Judge Uz. Ali Rasheed Hussain (Chair)
2) Judge Dr. Azmiralda Zahir
3) Judge Uz. Husnu Suood

• At this hearing, the Respondent was given the opportunity to respond to the State’s points of appeal.

• As such, although responses to most of the points of appeal were given in the available time, a further hearing was allowed by the Court to complete the response.

• A few of the responses given to rebut the State’s points of appeal are as follows.

1) Concern about omissions and confusions in the use and referencing of evidential materials and available information in the State’s appeal.

2) That this matter relating to a temporary injunction was submitted under s. 242(b)(2) of Law No. 32/2021 (Civil Procedure Code) requesting for an emergency order, 15 March 2024 marked 1 year without the case having  reached a conclusion.

3) The decision of the High Court on the matter of this temporary injunction is the most well researched, legally sound and professionally concluded decision of this type by a Maldivian court to date, involving environmental protection.

4) While the Appellant has argued that the High Court’s interpretation of the submitted case information is inaccurate, this interpretative inaccuracy is a problem not of the court but that of the Appellant.

5) That it is evident from the project EIA that the estimated cost of project monitoring was between USD1.7 – 1.8 million. However, the monitoring efforts fall below par given that a review of recently available monitoring reports show that elements such as sedimentation and others remain consistently outside the required parameters. The review report of the project monitoring reports was conducted by the Science Team at Environmental Law Alliance Worldwide (ELAW) for the Respondent.

6) The Appellant complained that in its decision, the High Court had not considered the current status of the project. In response, it was submitted that there is no notable improvement in the present condition to the previous condition based on the findings of the review of the monitoring reports, and that then and now, the effects of sedimentation is significant. When the current situation is considered, the present danger to the coral reefs are heighted due to increased global sea surface temperatures. Therefore, it was argued that what is needed when considering the current status is not just to stop the Gulhifalhu land reclamation project. It is both a moral and legal obligation for all concerned to halt all such reclamation activities inflicting reef damage in order to protect the coral reef ecosystems of the Maldives.

• The remaining responses to the points of appeal that was not completed at today’s hearing would be allowed at the next hearing, after which, the State will get the opportunity to respond to these rebuttals as noted by the Chair of the judges bench.

• The Supreme Court informed via email today that the next hearing is scheduled for 15 April 2024 at 10.15am, although this has since changed. A new hearing date is yet to be confirmed.
SC hearing 28 Mar 2024 [Miveshi Maldives]

19 Mar 2024

Miveshi Civil Court team [19Mar24]

Repeat of the 4th hearing of the main case held at the Civil Court on 13 March 2023 – Update

• One year ago on 13 March 2023, a hearing was held to submit witness testimony for the main (substantive) case. However, due to technical problems experienced by the court causing the recording files of that hearing to become corrupted (details of this in the 28 October 2023 update below) the court decided to repeat this hearing.
 
• As such, although efforts were made to schedule this hearing twice between August 2023 and now (that is, on 27 February 2024 and 7 March 2024), these hearing dates were cancelled for various reasons.
 
•  Therefore, on 10 March 2024, the court informed via email that a hearing was scheduled for today, 19 March 2024 at 10.30am. The hearing began at 10.41 and ended at 12.25pm. At the start of the hearing, Judge Uz. Farhad Rasheed apologized for the technical issues on behalf of the court, explaining that additional measures had been taken to prevent its repetition.
 
• This hearing was conducted to submit witness statements for the main case. Therefore, the two expert witnesses presented by the applicant, who gave evidence at the 13 March 2023 hearing who are esteemed and expert divers with special expertise and experience of Male’ atoll, Hussain Rasheed (Sendi) and Mohamed Seeneen (Sindhi) gave evidence at today’s hearing.
 
• The respondent (State) presented the  incumbent Director General of the Environmental Protection Agency (EPA) as their subject matter expert. The State claimed that Mr Naeem’s expert statements were not provided in his capacity as the head of the EPA, but rather solely as a subject matter expert. However, citing Law No. 11/2022 (The Evidence Act), we objected that this contravened multiple provisions of the law including s. 51 of the law which states that:

“Unless otherwise stated in a provision of this law, witness statements must not be taken from persons with a conflict of interest or in an adversarial position to any party in a case.” (unofficial translation)

However, the Judge stated that this dispute would be considered in evaluating the evidence and allowed the proceedings to continue. We accepted this with the caveat to proceed for the purpose of debate only.
 
• In contrast to the 13 March 2023 hearing, at today’s hearing, all persons giving witness statements were required to take an oath on the Quran. (On 13 March 2023, Mr Naeem was exempted from doing this, citing his position as an ‘expert witness’.) On that occasion, we made note of the discriminatory practice by the court in our update, and recognise this consistency towards all parties as a positive change.
 
• It is expected that after today’s hearing, it will take some time for the witnesses to sign their statements. No decision was taken about a date for the next hearing.

13 Mar 2024

State’s Appeal of the High Court’s Decision at the Supreme Court – Update – First Hearing

• Following the Supreme Court’s 15 February 2024 stay of execution order against the High Court’s 14 February 2024 decision, the State submitted its appeal of the High Court’s decision on the same day.
• As respondents in this case, we received the preliminary documents and the State’s appeal submissions for the case on 18 February 2024, with a deadline to submit our response by 29 February 2024.
• On 25 February 2024, we sent a request letter to the Supreme Court to extend the submission deadline to 7 March 2024 to enable the appointment of a lawyer and prepare our response. However, this request was rejected due to the urgency of the case and the court’s plan to hold the first hearing during the first week of March, as per the court’s response letter on 26 February 2024.
• As things turned out, on 7 March 2024, we received notice that the first hearing was scheduled for today, 13 March 2024.
• The hearing was scheduled for 9.15am today, 13 March 2024, and took place virtually via Microsoft Teams, from 9.45am to 10.28am.

• Today’s hearing was conducted by the Supreme Court’s following 3 judge bench:
1) Judge Uz. Ali Rasheed Hussain (Chair)
2) Judge Dr. Azmiralda Zahir
3) Judge Uz. Husnu Suood
• Today’s hearing was primarily for the Appellant (State) to submit its points of appeal and explain the details of the case to the court.
• As such, noting that the State’s explanatory  points of appeal raised certain questions that required factual and evidential clarity, we made two interventions to provide clarification to the court, which were allowed.

These were:
 1) Judge Uz. Husnu Suood asked the State to clarify whether the project contract included any clauses involving points of environmental protection as per the EIA.
– On this point, we provided factual information of news reports that the project contract was made in October 2019, and that the EIA commenced in December 2019 as per the EIA.
2) The State made repeated claims at this hearing that 80% of the project has been completed.
– On this point, we requested to know the evidential basis of this figure, as this conflicts with completion related numbers shared by the State at the 23 November 2023 hearing at the High Court. The court asked the State to clarify this point as well.
• As the respondent at this hearing is represented by Humaida, the Chair of the bench noted that we still have the opportunity to appoint a lawyer for the next hearing.
• The Chair of the bench said that the respondent will have the opportunity to respond to the State’s points of appeal at the next hearing. (No hearing date has been set at this time.)

13 March 2024 Supreme Court hearing
13 March 2024 SC Hearing

15 Feb 2024

Respondent (State) appeals High Court’s TSO decision at the Supreme Court which orders delaying implementation of the High Court judgment

Read Press Statement

Read our unofficial Translation of the Supreme Court’s Order (15 Feb 2024)

• On 15 February 2024, the State appealed the TSO decision of the High Court at the Supreme Court, which used its powers under section 21 of the Supreme Court’s Regulation issuing an order to delay the implementation of the High Court’s judgment for the moment.
• Section 21 of the Supreme Court’s regulation to ‘Delay the implementation of a judgment’ states (unofficial English translation):

“The Supreme Court has the power to temporarily halt the implementation of a judgment, an order or decision of the High Court where a submission is made to the Supreme Court with reasons which the Court deems acceptable.  However, the Supreme Court will take such action after an assessment of that judgment, order or decision by the assigned judges to the case and once that judges’ panel is satisfied that the best course of action is to halt implementation. As such, any application to delay the implementation of a judgment must be made using the Supreme Court’s relevant form for that purpose.”

• According to the regulation, the Supreme Court will take such action after a panel of judges establishes that halting implementation is the correct course of action. Therefore, the following 3 judge panel that issued the order found this to be the correct course of action.
– Judge Azmiralda Zahir
– Judge Ali Rasheed Hussain
– Judge Husnu Suood

• It is currently unclear what evidence the  Supreme Court relied upon to reach its decision. However, according to the order of that court, the reason for its decision is because:
“if the implementation of the Maldives High Court’s decision is not halted now, the probability of severe harm to the State is clearly evident.”
• According to some news reports on the High Court’s decision with reference to the State, every day that the Gulhifalhu reclamation works is stopped would incur ‘several million rufiyaa’ worth of damage. Notably, this is not a concern raised by the State during the court hearings of this case.
• In addition, section 6 of Law No. 4/93 (Maldives Environment Protection and Preservation Act) says the following in relation to project stoppage:

“The Ministry has the authority to terminate any project that has any undesirable impact on the environment. A project so terminated shall not receive any compensation.”

• Considering that Maldivian law clearly provides that there is no compensatory relief for stopping an ongoing project that has a negative impact on the environment, and given the use of such a reason to claim the State stands to suffer damages, the question arises as to what laws of what jurisdictions are applicable to the Gulhifalhu project.

14 Feb 2024

Special update: Civil Court TSO Decision Appeal at High Court – The High Court’s Decision

• The decision hearing about this case was scheduled for 9.00am at the High Court of the Maldives today, 14 February 2024, and took place between 9.25am and 10.15am. The following decision was issued by the 3 judge bench with the majority ruling by 2 judges.
1 – The decision overruled the TSO decision of the Civil Court of the Maldives of 8 June 2023 declaring that decision void.
2 – The court issued a temporary injunction or TSO for the respondent (the State) to halt the ongoing dredging and reclamation project at Gulhifalhu until the substantive case currently ongoing on this matter at the Civil Court is concluded.
3 – The 2 judges in favour of the decision are Judge Mohamed Shaneez Abdullah and Judge Huzaifa Mohamed. Judge Mohamed Niyaz issued his dissenting opinion.

We welcome the Court’s decision and plan to share further details in the coming days. The court’s decision is available below (Dhivehi original).
• However, we wish to make note of and celebrate the fact that in its decision, the court had given particular consideration to the ‘precautionary principle’ in international law by reviewing its history and providing a comprehensive review of the principle’s use and application in courts around the world. We are extremely happy and gratified that the High Court of the Maldives has taken the lead in upholding this principle for the first time in a national court, thereby setting this historic precedent.
• We also recognise that this is an important achievement in a public interest case relating to the defence of the fragile environment of the Maldives in a national court of law.

Humaida Abdul Qafoor Vs Ministry Environment

VIDEO: Humaida Abdul Qafoor Vs Ministry of National Planning, and Minister of Environment (2023/HC-A/267)

High Court’s Decision PDF (Dhivehi) [14 Feb 2024]

High Court’s Decision PDF (Unoffical English translation)
[added: 08 Apr 2024]

Extensive local news coverage (14 Feb):
Addu Live
Adhadhu
Avas.mv
CNM.mv
Dhauru News
Jazeera
MBR (now deleted)
Mihaaru
Sun.mv * EN
Sun.mv DHI
Raajje.mv
Thiladhun

23 Nov 2023

Civil Court TSO Decision Appeal at High Court – Update – 3rd hearing

• Following two cancellations of the scheduled hearings for 7th November and 16th November 2023, the hearing scheduled for today, 23 November 2023 at 11.00am took place at the High Court.
• Today’s hearing began at 11.20am and concluded at 12.25pm. The hearing was presided by the same bench of three judges as the first appeal hearing.
• Overall, today’s hearing involved responding to the questions from the bench by both parties. Time was given to answer questions from the bench to both parties about various points of law, arguments and evidential documentation provided about the appealed case.
• Due to the resignation of the lead Senior State Attorney in this case to date, Uz. Hammad Wafir,  the new lead State Attorney at today’s hearing was Uz. Ahmed Mohamed who had been supporting Uz. Wafir in this case. State Counsel Uz. Ahmed Nashath attended as an additional state representative.
• Concluding today’s hearing, Judge Uz Mohamed Shaneez Abdullah said that this is the final discussion hearing in this case, and the court’s decision would be announced at the next hearing. A date for the decision hearing is yet to be clarified.

Miveshi High Court Appeal (23 Nov 2023)

CASE TIMELINE
Humaida A Ghafoor v. Government of Maldives
Civil litigation to stop the Gulhifalhu Port Development Project, Maldives

Back to top 🔼